Project details
Project industry
electricity
Field type
Waste incineration power generation
Total budget investment
44.45 million yuan
Nature of investment
Non-governmental investment
Funds in place
Is being implemented
Project construction grade
Medium industry standard
It is expected to start construction year and month
2018
Expected year-end
2019
Provinces
Hunan
Local city
Loudi
Equipment source
domestic purchase
Progress stage
Approved for feasibility study
Business description
Project main equipment
Boilers, steam turbines, generators, condensers, soot blowers, garbage trucks, loadometers, cranes, garbage hoppers, grab cranes, incinerators, waste heat boilers, waste heat recovery boilers, pushback...
Project details
Loudi Municipal Solid Waste Incineration (Phase 1) Project (PPP),
1. Project construction address: Loudi City, Hunan Province.
2. Project Content: The construction scale of the project is to treat 1,050 tons of domestic garbage daily and implement it in two phases: the first-phase project scale is 700t/d (two 350t/d garbage incineration lines and one set of 12MW turbo-generator units are installed), and the second phase The project will be further increased by 350t/d (one 350t/d waste incineration line zx*w+ one 6MW steam turbine generator set).
3. The total investment of the first phase of the project: 443.54 million yuan.